Case Study: Bushnell Theater (Hartford, CT)

Case Study: Bushnell Theater (Hartford, CT)

Thursday, June 17, 2021 Buildings C-PACE Project Finance 0

Project Numbers:

  • Total C-Pace financing cost = $384,000 
  • Annual savings nearly $60,000

This study follows Lynn Robinson and David Fay who own and operate the Bushnell Theater in Hartford, CT. The owners were experiencing high energy costs due to a huge inefficient heating system that would be “all on, or all off.” They had even started buying used parts off of eBay before hearing about a C-PACE opportunity to replace their boilers. 

Through C-PACE, the owners chose a low-interest, long-term, fixed financing operation that allowed them to net a repayment and save a lot on utility costs.

 

 

 

 

 

Watch this brief video for more information:

Leave a Reply